Site A: later firm route
Connection evidence: Documented firm-capacity offer, subject to stated conditions.
Commercial question: Does the later start still meet the required return after delay sensitivity?
Technical question: Can delivery milestones and commissioning dependencies be met?
Decision today: Reference route for detailed diligence.
Site B: earlier flexible route
Connection evidence: Earlier flexible offer; curtailment limits and operating impact need validation.
Commercial question: Does earlier revenue outweigh restrictions, additional equipment and downside risk?
Technical question: Can the operating model meet connection conditions and contracted obligations?
Decision today: Keep as a conditional alternative until dispatch and contract risks are bounded.