CUSTOMER RESOURCE | DATA-CENTRE ENERGY STRATEGY

Data-centre power & reporting readiness checklist

Use this checklist before committing to a site, connection strategy or reporting workstream. Record what is documented, what remains an assumption and who will close each gap.

Download checklist PDF

Updated 16 October 2026 · Free download, no registration.

For each item, mark documented / needs review / missing. Keep the source, date, responsible person and next action. A public grid dataset can support screening; it cannot establish your connection rights.

01 Define the decision

  • What decision must be made, by when, and by whom? Compare sites, connection options or upgrades against the same commissioning target.
  • Record the facility boundary: installed IT power, total facility load, grid import/export capacity and planned expansion. These are different quantities.

02 Establish the route to power

  • Obtain the connection offer or documented status: capacity, expected date, validity, milestones, costs, dependencies and required works.
  • Compare firm and flexible options. Identify curtailment limits, notice periods, controllable loads, non-delivery consequences and any contractual compensation.
  • Test time-to-revenue against the downside of restricted operation. Keep an offered date separate from a verified, deliverable schedule.

03 Test the energy configuration

  • Compare BESS, generation and operational flexibility using a consistent baseline: capex, energy costs, operating costs, replacement needs and timing.
  • Model constraints before stacking revenues: power and energy limits, losses, degradation, reserves and availability obligations.
  • Quantify only supportable cash flows. Keep grid benefits and resilience outcomes visible without counting them as revenue unless a mechanism pays for them.

04 Prepare facility evidence

  • Map electricity, cooling, water, heat reuse and generation data to meters, owners and reporting periods. Record estimates and gaps.
  • For PUE (Power Usage Effectiveness) and WUE (Water Usage Effectiveness), confirm definitions, units, facility boundaries and time coverage before comparison. Record the treatment of shared infrastructure.
  • Separate current reporting requirements from future label readiness. Confirm applicable rules, thresholds and submission responsibilities for the facility and jurisdiction.

05 Review resilience and external dependencies

  • Map grid dependencies, physical and climate exposures, backup autonomy, redundancy and recovery assumptions. Include water and telecom dependencies.
  • Check whether dispatch flexibility can coexist with critical-load protection. Identify engineering validation, operational tests and partner expertise required.

06 Agree the next step

  • Create a short gap register: evidence missing, materiality to the decision, responsible person, cost and deadline to resolve.
  • Agree a software pilot: scenarios, data access, interfaces, report outputs, acceptance criteria and review checkpoints. Your appointed specialists validate the engineering inputs.

From checklist to software pilot

What a configured software pilot adds: your private project data, tailored scenarios, explicit assumptions and exportable report outputs with supporting data. xIntegra supports software configuration and data integration; your technical specialists validate the engineering inputs. Scope and acceptance criteria are agreed before work starts.

This checklist prepares a commercial and technical discussion. It does not issue an official label, establish eligibility, or guarantee grid access, permits or financing.