BCG · 18 August 2026
The value of being ready earlier
BCG examines Northwest Europe over 2030-2035. It combines four choices: where to locate, whether to accept a connection that can be curtailed, which workloads can move, and how much storage or generation to install behind the meter. Energy efficiency remains a starting point.
The key commercial finding is that earlier energisation can outweigh the added cost of onsite energy resources. Lower electricity bills alone often do not justify the change. A grid-positive design aims to limit additional system investment while making better use of existing infrastructure.
BCG also identifies the trade-offs: moving away from demand can add latency; curtailment needs a credible operating response; onsite resources need space, capital and permissions. Its findings support comparing whole delivery and operating models, rather than choosing a site on its electricity price alone. These are modelled scenarios, not an achieved return for a small modular project. [1]